# Martinez Refining Company (formerly Shell Martinez Refinery)

Martinez Refining Company (formerly Shell Martinez Refinery), Martinez, CA. 156,400 bpd crude capacity (EIA-820). Injects into Kinder Morgan SFPP; reaches 9 delivery points and 16 terminals by published tariff. Crude supply, outlets, events.

- Location: Martinez, CA
- Status: active
- Crude capacity: 156,400 bpd (EIA-820)
- Operator: Martinez Refining Company LLC
- Parent: PBF Energy Inc.

## Pipelines it injects into
- Kinder Morgan SFPP at Concord (research) — https://newtide.ai/supply/pipeline/kinder-morgan-sfpp/

## Reach by published tariff route
| Pipeline | Delivery points | Terminals | Lowest ¢/bbl | Median ¢/bbl |
|---|---|---|---|---|
| Kinder Morgan SFPP | 9 | 16 | 39.31 | 54.41 |

## Crude supply
- marine: Martinez Refining Company Marine Oil Terminal — The refinery's own wharf on Carquinez Strait. The California State Lands Commission assigned the wharf lease (PRC 4908.1) to Martinez Refining Company LLC by action of 6 December 2019, and describes tankers transferring oil and petroleum products to and from shore. The 2020 sale included a deep-water marine facility and about 8.8 million barrels of crude and product storage.

## Product outlets
- pipeline: Kinder Morgan SFPP — Kinder Morgan's Pacific Operations brochure (March 2025) draws 'PBF Martinez' as a third-party facility with a gathering line into Concord Station. Concord is the SFPP tariff origin and the start of the North Line. The brochure does not list products by feeder.
- truck_rack: Martinez Terminal Company LLC rack (IRS T-68-CA-4610) — The IRS terminal list shows Martinez Terminal Company LLC at 1801 Marina Vista, Martinez, under terminal number T-68-CA-4610. The list does not give the products loaded.
- marine: Martinez Refining Company Marine Oil Terminal — The State Lands Commission describes the wharf as a mooring for oil tankers transferring oil and petroleum products to and from shore. It has two active berths on the outer side and two inactive berths on the inner side. The products loaded are not itemised.

## Recent events
- 2025-06 — Independent investigation report concluded the February 2025 fire was caused by human error stemming from poor contractor training and supervision.
- 2025-03-06 — PBF announced two-stage restart plan: crude unit and other units in Q2 2025 (partial throughput 85,000-105,000 bpd), remaining units (including those scheduled for Q1 turnaround) by Q4 2025; ~$30M repair cost, largely insurance-covered.
- 2025-02-01 — Major fire near the catalytic feed hydrotreater (root cause: contractors opened the wrong flange during turnaround prep, releasing and igniting intermediate reflux); refinery fully shut down; fire extinguished Feb 4; six workers evaluated by medical personnel.
- 2023-11-19 — Furnace explosion/fire critically burned a contract worker; investigation found safety-system and alarm failures; approximately $350 million in property damage.
- 2022 — Release of approximately 50,000 pounds of powdered industrial chemicals into the air.

---
Source: Newtide Supply Explorer — https://newtide.ai/supply/refinery/martinez-refining-co-llc-martinez-ca/
Built from published FERC pipeline tariffs, EIA-820, the IRS Terminal Control Number list and sourced research. Rates are line-haul only. Cite as: Newtide, Supply Explorer, 2026-11-26.